2022 year
Bunter Group has completed installation of one of the two 019-P-1.1 and 019-P-1.2 furnace units manufactured for the condensate de-ethanization unit.
2021 year
Pre-commissioning works and mode adjustment of start-up and fuel gas heater PTPG-30M manufactured by Bunter Group has been carried out.
2021 year
Newly designed indirect heater has been manufactured and shipped to the Customer.
2021 year
Heater with intermediate coolant PPT-0.2G designed for heating oil emulsions in oil collection and transportation systems, as well as natural or associated gas and waste field water at gas-distributing units of gas-lift oil production system, has been manufactured and shipped to the Customer.
2021 year
Heaters PNPT-3.87 designed to heat oil and their mixtures in the system of collection, transportation, and preparation of well products has been manufactured and shipped to the Customer.
2021 year
Mobile indirect heating unit MUKN-0.12K was successfully commissioned.
2020 year
Capacitance water heater PVE-3.5 with heating capacity of 3.5 MW designed to heat water in the collection, transportation, and well product preparation systems is successfully operated.
2019 year
The customer needed a regeneration gas heating furnace as part of the gas treatment unit.
2019 year
The Customer faced a non-standard task: oil emulsion needed to be heated directly from the well pad in the absence of prepared fuel gas to feed the heater burners and the remaining infrastructure around the well pad.