The customer needed a regeneration gas heating furnace as part of the gas treatment unit.

According to the technical specifications, cylindrical furnace TsS-1-80-6.00 was suitable, but the customer required non-standard implementation of the project.

Special design solutions:

Furnaces of this design are usually placed outdoors. In this case, the main structures of the furnace had to be placed inside the process workshop building. This solution, in our experience, has no analogs. Its implementation required the development of non-standard algorithms of the furnace emergency protection due to the increasing number of explosive zones (inside the furnace, inside the building, and outside the building) and their combinations.

In accordance with the customer's assignment, the furnace is blown with nitrogen at -50 °C before start-up. This solution is also non-standard. The following measures were taken to maintain the operating capacity of the furnace after the low-temperature blowdown:

  • The coil is made of cryogenic steel;
  • The furnace seat lining is designed to withstand sudden temperature changes.

The furnace is made in a modular design which allowing to speed up the installation process as much as possible.

The furnace includes a gas analysis system to determine the concentration and amount of NOx, COx, and CH4 emissions in flue gases in all possible modes of furnace operation.

Would you like to discuss your project?

Our team is ready to implement a project of any complexity.
If you have assignments or questions, leave a request and we will contact you as soon as possible

Other projects
2020 year
The water heating boiler unit was shipped to the Customer in full factory readiness. The installation works are currently in final stages. The commissioning is scheduled for September 2020.
2016 year
Four sets of KDFT pipe end phase dividers designed for separation of well production and formation water treatment to the required standards were supplied.
2022 year
Works on re-equipment and replacement of the flare stack were performed.
2016 year
Flare unit designed for high-efficiency and high-quality combustion of periodic, permanent, and emergency discharges of combustible gases at oil and gas field treatment facilities in oil and gas fields, as well as oil, gas, and petrochemical industry enterprises, has been manufactured and shipped to the Customer.
2021 year
Mobile indirect heating unit MUN-4-PNPT-4.25 was commissioned, which is designed to heat liquid due to the increase in the amount of incoming liquid and change of its parameters

На этом веб-сайте используются файлы cookie, которые обеспечивают работу всех функций для наиболее эффективной навигации по странице. Если вы не хотите принимать постоянные файлы cookie, пожалуйста, выберите соответствующие настройки на своем компьютере. Продолжая навигацию по сайту, вы предоставляете свое согласие на использование файлов cookie на этом веб-сайте. Более подробная информация предоставляется в нашей политике конфиденциальности