Regeneration gas heating furnace

Regeneration gas heating furnace

Year
2019
Category
Oil and gas equipment

The customer needed a regeneration gas heating furnace as part of the gas treatment unit.

According to the technical specifications, cylindrical furnace TsS-1-80-6.00 was suitable, but the customer required non-standard implementation of the project.

Special design solutions:

Furnaces of this design are usually placed outdoors. In this case, the main structures of the furnace had to be placed inside the process workshop building. This solution, in our experience, has no analogs. Its implementation required the development of non-standard algorithms of the furnace emergency protection due to the increasing number of explosive zones (inside the furnace, inside the building, and outside the building) and their combinations.

In accordance with the customer's assignment, the furnace is blown with nitrogen at -50 °C before start-up. This solution is also non-standard. The following measures were taken to maintain the operating capacity of the furnace after the low-temperature blowdown:

  • The coil is made of cryogenic steel;
  • The furnace seat lining is designed to withstand sudden temperature changes.

The furnace is made in a modular design which allowing to speed up the installation process as much as possible.

The furnace includes a gas analysis system to determine the concentration and amount of NOx, COx, and CH4 emissions in flue gases in all possible modes of furnace operation.

Would you like to discuss your project?

Our team is ready to implement a project of any complexity.
If you have assignments or questions, leave a request and we will contact you as soon as possible

Other projects
2022 year
Bunter Group has completed installation of one of the two 019-P-1.1 and 019-P-1.2 furnace units manufactured for the condensate de-ethanization unit.
2019 year
This is an auxiliary unit for operation of the main equipment of booster compressor station (BCS).
2020 year
A recuperator unit designed for beneficial use of the combustion heat of excessive flow of associated petroleum gas has been shipped.
2020 year
Capacitance water heater PVE-3.5 with heating capacity of 3.5 MW designed to heat water in the collection, transportation, and well product preparation systems is successfully operated.
2021 year
Mobile indirect heating unit MUN-4-PNPT-4.25 was commissioned, which is designed to heat liquid due to the increase in the amount of incoming liquid and change of its parameters

На этом веб-сайте используются файлы cookie, которые обеспечивают работу всех функций для наиболее эффективной навигации по странице. Если вы не хотите принимать постоянные файлы cookie, пожалуйста, выберите соответствующие настройки на своем компьютере. Продолжая навигацию по сайту, вы предоставляете свое согласие на использование файлов cookie на этом веб-сайте. Более подробная информация предоставляется в нашей политике конфиденциальности